Initiation of Site Characterization
January 2012
Completion of Basic Design
July 2013
Public Information Session Held
May 2014
Commencement of Detailed Design
May 2014
Application and Approval for Construction and Operation License
December 2015
Approval of Electric Power Project Implementation Plan
July 2016
Completion of Site Preparation Work
December 2017
Acquisition of Construction and Operation License
July 2022
Groundbreaking Ceremony Held
August 2022
Project Completion Scheduled
December 2025 (Planned)