Site Selection for LILW Disposal Facility
November 2005
Official Designation of Planned Electric Power Development Project Area
January 2006
Approval of Electric Power Development Project Implementation Plan
July 2007
Construction and Operation Permit for Radioactive Waste Disposal Facility and Groundbreaking
Permit (July 2008) & Groundbreaking (August 2008)
Transfer of Construction Project [KHNP → KORAD]
January 2010
Approval for Priority Use of the Facility
- Priority Use of Receipt & Storage Building (December 2009)
- Use Service Building (December 2010)
First Receipt of Radioactive Waste (1,000 Drums from Uljin)
December 2012
Construction Completed
June 2014
Final Inspection of Main Facility Construction
July 2014
Approval for Opreation of Disposal Facility (by NSSC)
December 2014
First Disposal of LILW
July 2015